Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
---|
|
County | LAMAR | Highway | US0082 | From | US 82 W | To | US 271 N | CSJ | 6203-38-001 | Proj ID | RMC - 620338001 | Work Type | SEAL COAT SHOULDERS/CLEAN & SEAL JOINTS | |
| 3.560 | 372768.26 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 00-00-00 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 40 | Addl Days Granted | 0 | Working Days Charged | 0 | Percent Time Used | 0 | Contractor(s) | BRANNAN PAVING CO., LTD. | SUBCONTRACTOR(S) FOR CCSJ: 6203-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 05104002 |
| Totals | 372768.26 | 0.00 | 0.00 | 0.0 |
|
County | LAMAR | Highway | US0082 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6388-72-001 | Proj ID | RMC - 638872001 | Work Type | PAINT | |
| 0.010 | 1559210.00 | | 3328704.72 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 02-01-22 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 254 | Addl Days Granted | 254 | Working Days Charged | 382 | Percent Time Used | 75 | Contractor(s) | STRIPING TECHNOLOGY, L.P. | SUBCONTRACTOR(S) FOR CCSJ: 6388-72-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 11214023 |
| Totals | 1559210.00 | 502825.42 | 3328704.72 | 99.9 |
|
County | HUNT | Highway | IH0030 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6388-73-001 | Proj ID | RMC - 638873001 | Work Type | PAINT | |
| 0.010 | 1536660.00 | | 2945132.75 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 02-01-22 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 254 | Addl Days Granted | 254 | Working Days Charged | 317 | Percent Time Used | 62 | Contractor(s) | STRIPING TECHNOLOGY, L.P. | SUBCONTRACTOR(S) FOR CCSJ: 6388-73-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 11214222 |
| Totals | 1536660.00 | 464390.69 | 2945132.75 | 99.9 |
|
County | HUNT | Highway | IH0030 | From | VARIOUS LOCATIONS IN | To | HUNT AND RAINS COUNTY | CSJ | 6393-38-001 | Proj ID | RMC - 639338001 | Work Type | TRAFFIC CONTROL SERVICES | |
| 0.010 | 1511217.50 | | 1349420.30 | 89.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 11-01-22 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 639 | Percent Time Used | 87 | Contractor(s) | AREA WIDE PROTECTIVE, INC. | SUBCONTRACTOR(S) FOR CCSJ: 6393-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 06224427 |
| Totals | 1511217.50 | 116212.86 | 1349420.30 | 89.2 |
|
County | LAMAR | Highway | US0082 | From | VARIOUS LOCATIONS IN | To | LAMAR, DELTA AND RED RIVER COUNTY | CSJ | 6393-40-001 | Proj ID | RMC - 639340001 | Work Type | TRAFFIC CONTROL SERVICES | |
| 0.010 | 1236500.00 | | 2279997.50 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 11-01-22 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 639 | Percent Time Used | 87 | Contractor(s) | AREA WIDE PROTECTIVE, INC. | SUBCONTRACTOR(S) FOR CCSJ: 6393-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 06224614 |
| Totals | 1236500.00 | 133340.00 | 2279997.50 | 99.9 |
|
County | GRAYSON | Highway | US0069 | From | VARIOUS LOCATIONS IN | To | GRAYSON COUNTY | CSJ | 6393-41-001 | Proj ID | RMC - 639341001 | Work Type | TRAFFIC CONTROL SERVICES | |
| 0.010 | 963650.00 | | 1302456.25 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 09-01-22 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 700 | Percent Time Used | 95 | Contractor(s) | BARRICADES UNLIMITED | SUBCONTRACTOR(S) FOR CCSJ: 6393-41-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 06224213 |
| Totals | 963650.00 | 91317.50 | 1302456.25 | 99.9 |
|
County | HUNT | Highway | IH0030 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6396-92-001 | Proj ID | RMC - 639692001 | Work Type | LARGE SIGN REPLACEMENT | |
| 0.010 | 342157.00 | | 350318.50 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 09-09-22 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 254 | Addl Days Granted | 254 | Working Days Charged | 341 | Percent Time Used | 67 | Contractor(s) | SOUTHERN CROSS CONTRACTORS, LLC | SUBCONTRACTOR(S) FOR CCSJ: 6396-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 04224223 |
| Totals | 342157.00 | 89463.75 | 350318.50 | 99.9 |
|
County | GRAYSON | Highway | US0075 | From | VARIOUS LOCATIONS IN | To | GRAYSON COUNTY | CSJ | 6419-87-001 | Proj ID | RMC - 641987001 | Work Type | DEBRIS REMOVAL | |
| 0.010 | 479285.00 | | 738677.00 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 12-19-22 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 591 | Percent Time Used | 80 | Contractor(s) | ANTHONY SERVICES | SUBCONTRACTOR(S) FOR CCSJ: 6419-87-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 10224217 |
| Totals | 479285.00 | 39545.00 | 738677.00 | 99.9 |
|
County | HUNT | Highway | US0069 | From | VARIOUS LOCATIONS IN | To | HUNT AND RAINS COUNTIES | CSJ | 6425-88-001 | Proj ID | RMC - 642588001 | Work Type | DITCH CLEANING AND RESHAPING | |
| 0.010 | 364225.00 | | 910556.75 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 04-24-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 465 | Percent Time Used | 63 | Contractor(s) | TEXAS DRAINAGE INC. | SUBCONTRACTOR(S) FOR CCSJ: 6425-88-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 02234215 |
| Totals | 364225.00 | 0.00 | 910556.75 | 99.9 |
|
County | HUNT | Highway | IH0030 | From | IH 30 THROUGH | To | HUNT, HOPKINS, AND FRANKLIN CO. | CSJ | 6427-05-001 | Proj ID | RMC - 642705001 | Work Type | DEBRIS REMOVAL | |
| 0.010 | 319133.00 | | 366726.00 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 06-01-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 427 | Percent Time Used | 58 | Contractor(s) | MORTON ENTERPRISE | SUBCONTRACTOR(S) FOR CCSJ: 6427-05-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 04234213 |
| Totals | 319133.00 | 32852.50 | 366726.00 | 99.9 |
|
County | LAMAR | Highway | US0082 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6433-52-001 | Proj ID | RMC - 643352001 | Work Type | PAVEMENT MARKINGS | |
| 0.010 | 471520.00 | | 181623.01 | 38.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 06-01-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 426 | Percent Time Used | 58 | Contractor(s) | | SUBCONTRACTOR(S) FOR CCSJ: 6433-52-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 03234030 |
| Totals | 471520.00 | 0.00 | 181623.01 | 38.5 |
|
County | HOPKINS | Highway | IH0030 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6433-54-001 | Proj ID | RMC - 643354001 | Work Type | PAVEMENT MARKINGS | |
| 0.010 | 461060.50 | | 136165.99 | 29.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 07-05-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 365 | Working Days Charged | 393 | Percent Time Used | 53 | Contractor(s) | TRAFFIC HIGHWAY MAINTENANCE, LLC | SUBCONTRACTOR(S) FOR CCSJ: 6433-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 03234231 |
| Totals | 461060.50 | 0.00 | 136165.99 | 29.5 |
|
County | LAMAR | Highway | US0082 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6434-84-001 | Proj ID | RMC - 643484001 | Work Type | ILLUMINATION MAINTENANCE | |
| 0.010 | 439885.30 | | 96422.50 | 21.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 12-01-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 254 | Addl Days Granted | 0 | Working Days Charged | 170 | Percent Time Used | 66 | Contractor(s) | YUNEX LLC | SUBCONTRACTOR(S) FOR CCSJ: 6434-84-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 06234035 |
| Totals | 439885.30 | 0.00 | 96422.50 | 21.9 |
|
County | HOPKINS | Highway | IH0030 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6440-51-001 | Proj ID | RMC - 644051001 | Work Type | FULL DEPTH CONCRETE REPAIR | |
| 0.010 | 2947460.00 | | 1908449.38 | 64.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 01-29-24 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 138 | Addl Days Granted | 0 | Working Days Charged | 65 | Percent Time Used | 47 | Contractor(s) | WINDING ROAD CONSTRUCTION, INC. | SUBCONTRACTOR(S) FOR CCSJ: 6440-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 08234032 |
| Totals | 2947460.00 | 295776.31 | 1908449.38 | 64.7 |
|
County | GRAYSON | Highway | US0069 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6441-62-001 | Proj ID | RMC - 644162001 | Work Type | FLEXIBLE PAVEMENT STRUCTURE REPAIR | |
| 0.010 | 4219509.82 | | 2300457.54 | 54.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 09-01-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 254 | Addl Days Granted | 0 | Working Days Charged | 229 | Percent Time Used | 90 | Contractor(s) | D. L. LENNON INCORPORATED - CONTRACTOR | SUBCONTRACTOR(S) FOR CCSJ: 6441-62-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 06234623 |
| Totals | 4219509.82 | 663751.89 | 2300457.54 | 54.5 |
|
County | HUNT | Highway | IH0030 | From | VARIOUS LOCATIONS IN | To | HUNT, RAINS, HOPKINS, AND FRANKLIN CO. | CSJ | 6441-97-001 | Proj ID | RMC - 644197001 | Work Type | METAL BEAM GUARD FENCE REPAIR | |
| 0.010 | 719833.00 | | 850628.50 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 09-01-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 0 | Working Days Charged | 335 | Percent Time Used | 91 | Contractor(s) | ROSS SA ENTERPRISE LLC | SUBCONTRACTOR(S) FOR CCSJ: 6441-97-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 06234209 |
| Totals | 719833.00 | 382607.00 | 850628.50 | 99.9 |
|
County | LAMAR | Highway | FM0137 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6443-16-001 | Proj ID | RMC - 644316001 | Work Type | MILL AND INLAY | |
| 0.010 | 6031608.55 | | 3473335.42 | 57.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 12-06-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 114 | Addl Days Granted | 0 | Working Days Charged | 113 | Percent Time Used | 99 | Contractor(s) | RICHARD DRAKE CONSTRUCTION COMPANY, L.P. | SUBCONTRACTOR(S) FOR CCSJ: 6443-16-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 06234425 |
| Totals | 6031608.55 | 537145.31 | 3473335.42 | 57.5 |
|
County | GRAYSON | Highway | US0075 | From | VARIOUS LOCATIONS | To | PARIS DISTRICT | CSJ | 6445-19-001 | Proj ID | MMC - 644519001 | Work Type | DE-ICING SALT | |
| 0.010 | 891158.00 | | 86829.23 | 9.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 09-18-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 182 | Addl Days Granted | 182 | Working Days Charged | 318 | Percent Time Used | 87 | Contractor(s) | NSG LOGISTICS, LLC | SUBCONTRACTOR(S) FOR CCSJ: 6445-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 08234033 |
| Totals | 891158.00 | 0.00 | 86829.23 | 9.7 |
|
County | LAMAR | Highway | US0082 | From | VARIOUS LOCATIONS IN | To | PARIS DISTRICT | CSJ | 6445-37-001 | Proj ID | RMC - 644537001 | Work Type | RAISED PAVEMENT MARKERS | |
| 0.010 | 536512.00 | | 33137.00 | 6.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 02-26-24 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 365 | Addl Days Granted | 0 | Working Days Charged | 157 | Percent Time Used | 43 | Contractor(s) | BRYDL CONTRACTING, LLC | SUBCONTRACTOR(S) FOR CCSJ: 6445-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 12234036 |
| Totals | 536512.00 | 0.00 | 33137.00 | 6.1 |
|
County | HUNT | Highway | US0069 | From | VARIOUS LOCATIONS | To | IN HUNT & RAINS COUNTIES | CSJ | 6447-22-001 | Proj ID | MMC - 644722001 | Work Type | DENSE GRADED HOT MIX | |
| 0.010 | 439560.00 | | 45597.02 | 10.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN | Work Order | 00-00-00 | Work Began | 10-11-23 | Work Completed | | Time Computed | 00-00-00 | Contract Working Days | 120 | Addl Days Granted | 240 | Working Days Charged | 295 | Percent Time Used | 81 | Contractor(s) | RK HALL, LLC | SUBCONTRACTOR(S) FOR CCSJ: 6447-22-001 NO SUBCONTRACTORS FOR THIS CCSJ
| Contract # | 08234225 |
| Totals | 439560.00 | 0.00 | 45597.02 | 10.3 |
|